# Create an ASSET-only Production
Now that you have designed your workflow in Kitsu and invited more people, it's time to create your production.
Click on the Create a new production button.
Enter your production name, and choose only Asset as the type, then select the style of your production (2D, 3D).
Then, you must fill in technical information, such as the number of FPS, the Ration, and the Resolution.
All these data will be used when Kitsu re-encodes the video previews uploaded.
Then, you need to define your production's start and end dates.
You can define your production workflow in the next part, 3 to 6.
You need to select your asset task type (3), task status (4), and asset types (5).
TIP
To create your Production Workflow, you will select Task Types from the Global Library.
If you realize you missed some Task Types, you will be able to create them later.
See the Studio Workflow section.
Then, 6 is the option part. If you already have a spreadsheet with your Asset.
See the import CSV section for more details.
Validate everything with the button.
# Introduction to the Kitsu Global Page
Welcome to Kitsu's global asset page.
Let's take a look around.
On the top part (1), you have the global navigation, which is always visible throughout all the production pages.
From left to right:
# Main Menu
By clicking on the top left button, Kitsu (or your Studio logo), you will open the Main Menu.
On the Main Menu, you will find direct access to your assigned tasks, productions, global and team schedules, the workflow customization page, and the Kitsu settings.
Main Menu Details
WORKSPACE
- My Tasks: your assigned tasks
- My Checks: All the tasks with status Is Feedback Request depending on your department(s)
- My Productions: Get back to the selection on the production page.
STUDIO
- Productions
- People
- Timesheets
- Main Schedule
- Team Schedule
- All tasks
- News Feed
- Entity Search
ADMIN
- Departments
- Task Types
- Asset Types
- Custom Actions
- Automation
- 3D Backgrounds
- Bots
- Settings
- Logs
Permission Visibility
The WORKSPACE section is enabled for all permissions except My Checks, which artists do not see.
Artist (and above) can also see their own Timesheets, and have access to the Entity Search
# Navigation
You will see the navigation dropdown menu on the right of the main menu icon.
You can choose between production. The name of the actual production and actual page are always displayed.
You can use the dropdown menu to navigate from production to production (if you have several).
Once you have selected a production, the next dropdown menu will help you navigate through the different pages of this production.
Navigation details
The first section is about the tracking of your tasks
- Assets
- Edits (If you have created specific tasks)
The second section is more about the side of the production
- Concepts
- Breakdown
- Playlists
- News feed
The third section is about statistics
- Asset Type Stats
The fourth section is related to Team Management
- Schedule
- Quotas
- Team
The fifth section is about the settings of your production
- Settings
TIP
You start with the asset page, but you can change your production homepage to other entities (see setting page)
WARNING
If you realize you need an extra level of navigation, such as Episodes, you need to change your production Type to a TV Show.
If, on the contrary, you realize you need the shots, you also need to switch your production type from Only Assets to Short.
# Global Search, News, Notification and Documentation
You have the global search on the right of the navigation dropdown menu. It's a quick access search that will display the four first results. If you need more results and filtering options, see the Entity Search page.
The next icon is a direct link to our news and feedback page.
You can see all the new features with an animated gif and also add suggestions about the next feature you want to see in Kitsu.
Next, the bell icon displays your notifications (assignments, comments, tags). The number of unread notifications will be shown on the bell icon. There are various filters to help you stay on top of updates and revisit important ones when needed. You can easily mark notifications as read or unread or quickly filter by watching/non-watching to focus on what matters most and declutter your feed.
The last icon before your avatar is the documentation button. , that you are reading right now!
# Personal Settings
You can click on your avatar to open your menu (setting, documentation, etc.).
.
# The Tasks Spreadsheet
# Entity spreadsheet
The second part of the screen is common to all the entities (Asset, shot, sequence, Edit). This is the global tasks spreadsheet.
Here, you see the status, assignation, priority, etc, for each task.
TIP
The first line and column header of the spreadsheet always appear at the top of the page, even if you scroll down.
You can also Stick other columns to keep them visible at all times.
# Filters
The first element on the left is the filter box. You can type anything you want for simple filtering, sequence, asset type, etc.
If you need more advanced filtering, please use the filter builder button.
You can then save all the filters and use them as your pages.
# Simplify the display
On the right part of the screen, there are some buttons (from left to right) to hide or display the assignation, hide or display the extra column, enlarge or reduce the thumbnail,
# Import / Export
batch import thumbnail , and finally import or export data.
# Metadata column
Below, you have the name of the column. the (+) next to Name is here to create a new metadata column. Then, you have the name of the task type column.
# Customize the view
On the far right of the screen, next to the scroll bar, is the option to hide and display a text column
.
# Sum-up of your view
The last part (4), at the bottom of the screen, is the sum-up of your displayed page. It means the sum-up will update if you filter the page.
You can see the number of elements (assets or shots), the total number of estimated days, and the total number of days already spent.
# Create an Asset
# Create your first Asset
So, now that we have created our production and have a general grasp of the Kitsu interface, it's time to create our very first Asset.
On the asset page, click on Add assets.
WARNING
When you create an asset, your task workflow will be applied, and all the tasks will be created simultaneously as the Asset.
A pop-up window opens:
It asks you to choose the Asset Type (1). If you didn't add a new asset type, Kitsu will provide you with examples such as Characters, Environment, FX, Props, etc. Let's start with a character.
TIP
You can also customize the asset type list and the tasks pipeline. See the guide ( Customization of the workflow) for more details
We give it a Name (2) and enter a description that helps the Artist know what to do and quickly identify the Asset.
Click on Confirm and stay if you have multiple assets to create.
You can change the asset type and keep adding assets.
TIP
The newly created Asset appears in the background whenever you click on Confirm and stay.
After adding your last Asset, click on Confirm. It will create the Asset and close the window.
TIP
If you click on **Confirm and stay ** but realize you don't have more assets to add, click on Close, and the winwill bew is canceled.
You will also see the tasks that are selected for your assets workflow are created at the same time.
If you need to add more Assets, click the + Create assets button.
Create Assets from a CSV Spreadsheet File
You may already have your asset list ready in a spreadsheet file.
With Kitsu, you have two ways to import them; the first is to import a .csv
file and copy-paste your data directly into Kitsu.
First, save your spreadsheet as a .csv
file.
Then, go back to the asset page on Kitsu and click on the Import icon.
A pop-up window Import data from a CSV opens. Click on Browse to pick your .csv
file.
To see the result, click on the Preview button. You can check and adjust the name of the columns by previewing your data. NB: the Episode column is only mandatory for a TV Show production.
Once everything is good, click the Confirm button to import your data into Kitsu.
Now, you have imported all your assets into Kitsu and created the task according to your Settings.
Create Assets by Copying / Pasting a Spreadsheet File
Open your spreadsheet, select your data, and copy them.
Then, go back to the asset page on Kitsu and click on the Import icon .
A pop-up window Import data from a CSV opens; click on the Paste a CSV data tab.
You can paste your previously selected data and see the result with the Preview button. You can check and adjust the name of the columns by previewing your data. NB: the Episode column is only mandatory for a TV Show production.
Once everything is good, click the Confirm button to import your data into Kitsu.
Now, you have imported all your assets into Kitsu and created the task according to your Settings.
# See the Details of an Asset
To see an asset's detail, click on its name.
A new page opens with the list of the tasks, the assignation, and the status newsfeed on the right.
You can click on the status of each task to open the comment panel and see the history of the comments and the different versions.
You can also access the Casting,
concept linked to this Asset,
The Schedule is available if you have previously filled out the task type page data. If the data have already been filled out, you will be able to modify them directly here.
the Preview Files uploaded at various task types,
And the Timelog if people have filled out their timesheet on the tasks of this Asset.
# Add more tasks after creating the assets
If you realize after creating the assets that the task is missing, you can still add them.
First, be sure that the missing task type is added to the settings page under the task type tab.
Then go back to the asset page and click on + Add tasks
### Update your assets At any point, you can update your assets, change their name and asset type, modify their description, and any custom information you added to the global page.
You can edit assets by going to the asset page, hovering over the Asset you want to modify, and then clicking on the edit button (1) on the right side of the line.
To extend the description on the main asset page, click on the first words (2), and a pop-up with the full description will open.
Update Assets with the CSV Import
You can use the CSV import to update your data quickly.
You can update the type of an asset, the Assignation, the Status of tasks, and add a Comment.
You need to switch on the option Update existing data. Then the lines that will be updated will be highlighted in blue.
Update Assets by Copying / Pasting a Spreadsheet File
Open your spreadsheet, select your data, and copy them.
Then, go back to the asset page on Kitsu and click on the Import icon .
A pop-up window Import data from a CSV opens; click on the Paste a CSV data tab.
You can paste your previously selected data and see the result with the Preview button. You can check and adjust the name of the columns by previewing your data.
NB: the Episode column is only mandatory for a TV Show production. You need to switch on the option Update existing data. Then, the lines that will be updated will be highlighted in blue.
Now, you have imported all your assets into Kitsu and created the task according to your Settings.
# Create a Concept
# Upload a Concept
To create a Concept, go to the Concept page with the navigation menu.
To upload a concept, click the Add a new reference to concepts button.
You can upload one or several concepts at the same time.
Once you upload your previews, the concept page will look like this.
You can interact with the concept in two ways: click on the picture to see an enlarged view. The second is to click on the status part to open the Comment Panel on the right.
On the comment panel, you have two options: link a concept to an existing asset or delete it. You can also comment and change the status of the Asset.
The idea is to have one version per Concept. If it's not approved, you need to upload a new concept, not to have multiple versions of the same concept.
One concept is one task.
# Link a Concept to an Asset
Once concepts are uploaded, you can link them to the assets.
You can see the links on the status part of the assets.
Click on the status part of the concept; it will open the comment panel on the right.
On the comment panel, you have two options at the top: Link a concept to an asset and delete the concept.
To link an asset, click on the Link button.
Kitsu will display all the Assets available to link with the concept uploaded.
Kitsu will list the linked assets at the top of the comment panel. For now, there are No Links.
To link an asset, you have to click on it. The linked assets' names will appear at the top of the screen and under the preview of the concept.
Once a concept is linked to an asset, it can be seen on the asset's detail page.
Return to the asset page, and click on the asset name you want to see the concept.
Per default, the casting detail is displayed on the second part of the screen. Use the dropdown menu to choose the concept.
Once in the concept section, you will see all the concepts created for this Asset. You can filter them per status.
# Create Custom Metadata Columns
To add more information on the general spreadsheet pages, you must create a custom metadata column.
You may have extra information to add to your pages, such as the level of difficulties, Weather, Tag, etc. You can store all text (or number) information in the custom metadata column.
Click on the + near the Name column.
With the Type option, you can choose how you want to store your information:
- a free Text,
- a Number,
- a Checkbox,
- a List of value,
- a List of tags,
- a Checklist.
WARNING
The Text, Number, and Checkbox allow you to add different information for each entity. You don't have to plan it first.
The List of value, List of tags, and Checklist give you the same choice for each entity. Moreover, it has to be filled now.
Type the list elements below Available values, and confirm them by clicking on Add value.
You can also link the metadata column to one or several departments.
TIP
Link a metadata column to a department. The artists/supervisors will see it on their to-do page and in the department-filtered view.
You can link the metadata column to one or more departments. Click on the department from the list and then click on add to be effective.
Here, the VFX column is linked to two departments.
Edit meta column
On the global page of the Asset or the shot, click on the arrow to the right of your metadata column and click on Edit.
You can fill in this information directly on the global spreadsheets page. The cases are editable.
TIP
You can batch-modify the metadata column by selecting several entities on the left and then modifying your metadata column.
Edit by hand
You can also modify the information with the edit button .
You now see a new line on the edit pop-up. You can select the information from the list, alternatively, enter the free text or number, check a box, or use the checklist, depending on your previous choice.
Remember to press the Confirm button when you are done.
Go to the general spreadsheet page if you need to edit or delete the metadata column. Nearby the name of your metadata column, click on the arrow .
TIP
You can sort your global page with this new column. Click the arrow on the right of the column name to open his menu. Then click on Sort By.
You can also Stick the metadata column to the left.
# Create an Edit
You can track tasks at the Edit Level in Kitsu.
It's especially useful when You have several edits to track through several validation steps. For example, you can track your whole movie, several trailers, and the First Edit, Fine Edit, Mix, etc.
WARNING
Per default, the Edit page will not be displayed until you have task types for it on your production library (setting page)
To use this page, you need to first create a dedicated task type on your Global Library with the Edit attribute.
See Pipeline customization Section to create a new Task Type.
Once you have created your Task Types on your Global Library, add them to your Production Library, you will see the Edit displayed on the navigation drop-down menu.
This new page behaves like the Asset and Shot global page. You can add your edits with the + New edit button.
You can assign tasks, do the review, change status, etc.
You can add a metadata column, fill in the description, etc.
TIP
Depending on your deliveries, you can also change the resolution per Edit.
WARNING
The detail page is different from the other entities.
As Edit focuses on a specific long video, the detail page looks more like the comment detail page.
You can Rename and Delete the Edit entity on this page, as you can for the Asset and shot entities.
# Create a Breakdown List
Filling out the breakdown helps you with the assembly of the Asset. With the breakdown, you have all the details of the assets you need to add to create your main Asset and we are sure we will omit nothing.
On the dropdown menu, choose BREAKDOWN.
On the left of the breakdown page is the asset menu (1); you can choose between those you created. They are the right part of the screen; all the assets created are available for this production (3). Moreover, in the middle section, your selection for the Asset (2).
So now you have to select the Asset you want to cast.
You can display the assets as text if you don't have thumbnails yet or enlarge the thumbnails size.
You may also realize an asset needs to be added to the list during your breakdown.
You can create a new asset directly from the breakdown page. Click the + on the right of the All available assets.
You can also select multiple assets at once. Click on the first Asset, hold the shift key, and click on the last Asset of your selection.
Then click on the assets you want to assign: characters, backgrounds, ... from the right part (3). If you have selected multiple assets, your selection is applied to the numerous assets.
Copy an asset filled with assets and paste this asset selection into another asset.
You can see a +1 or +10 when you pass over the Asset. It's the number of times you add this Asset, and you can click on it as many times as you need.
You can now see the Asset in the middle of the screen (2). Next to the Asset's name is the number of times it has been added. In this example, we have added the character asset Llama two times.
If you add an asset twice by mistake, you must go to the screen's middle part to select assets for this shot (2). From there, click on -1. When you finish this shot, go on with the other shots. Your selection is automatically saved.
If a new asset is created during the task, return to the asset page (using the dropdown menu) and create the needed assets. The tasks previously created are applied immediately to these new assets. However, you have to do the assignment, and then you can continue with the breakdown.
Now, your Breakdown page should look like this.
Create a Breakdown List from a CSV File
You may already have your breakdown list ready in a spreadsheet file. With Kitsu, you have two ways to import it: the first is to import a .csv file directly, and the second is to copy-paste your data directly into Kitsu.
First, save your spreadsheet as a .csv
file following Kitsu's recommendation.
Click on the import button
A pop-up window Import data from a CSV opens. Click on Browse to pick your .csv
file.
To see the result, click on the Preview button.
You can check and adjust the name of the columns by previewing your data.
NB: the Episode column is only mandatory for a TV Show production.
Once everything is good, click the Confirm button to import your data into Kitsu.
Now, you have your breakdown imported into Kitsu.
Create a Breakdown List by Copying / Pasting a Spreadsheet File
Open your spreadsheet, select your data, and copy them.
Then, go back to the breakdown page on Kitsu, and click on the Import icon .
A pop-up window Import data from a CSV opens; click on the Paste a CSV data tab.
You can paste your previously selected data and see the result with the Preview button. You can check and adjust the name of the columns by previewing your data. NB: the Episode column is only mandatory for a TV Show production.
Once everything is good, click the Confirm button to import your data into Kitsu.
Now, all your assets have been imported into Kitsu.